Fernwood House, Essex

Job Specification

Major Refurbishment Works of existing 2 Floor Office Block

Name of Project

Fernwood House, Essex

Area of works

Approx. 4,350 sq. ft

Description of Works

  • Strip out of existing asbestos sheet roof, guttering and down
    pipes
  • Removal of existing chimney stack down to roof level
  • Removal of existing windows (part windows)
  • Removal of existing internal masonry and timber stud walls
  • Removal of existing floor coverings
  • Removal of existing kitchen areas
  • Removal of existing M&E services
  • Removal of existing electrical services
  • Removal of internal timber staircase to front reception area
  • Removal of steel columns
  • Installation of new Kingspan metal roof, guttering and down
    pipes
  • Installation of new windows and doors
  • Infill of existing masonry openings
  • New external water mains upgrade
  • New stud partition walls throughout
  • New structural steel works as per building control approval
  • New suspended ceilings throughout
  • New heating system throughout
  • New drainage for WC’s and kitchen areas
  • New lighting throughout
  • New power, data, fire alarm system, earthing and bonding, door entry system
  • New extractor fans to all WC’s
  • New sanitaryware to all WC’s
  • New WC cubicles
  • New external cladding to West elevation
  • New disabled ramp to main entrance
  • New internal door sets including ironmongery
  • New timber skirting and architraves throughout
  • DOFF Cleaning to external brick work
  • Decorations throughout
  • New kitchens to ground and first floor levels
  • New floor coverings throughout
What We Did

Job Gallery

Here are some before and after images.

Before

After

More Finished Images

Testimonial

Steve and the team at MASC are highly skilled contractors and were a joy to work with throughout our large scale refurbishment work within our new office. We took a former disused commercial building and created our new office space for our thriving Essex Team. We were delighted with the end result. MASC delivered our project ahead of time and handled the challenges associated with this type of refurbishment with solutions and positive thinking. The quality of workmanship and the team were a pleasure to work with. Our fantastic new office space provides us with larger facilities for our growing workforce and strengthens our service capabilities for our customers.

Debbie ClareCommercial Director